Daily Log December 2, 2011


Who was on site
Larry, Doug, Steve, Bert, Chris, Peter, Susan and Vince (Project Manager –reporting).
From Muskoka Exteriors: Darren and Brian.

What Happened 

The siding team made some great head way we have approximately one and a half walls complete.  New volunteer, Susan, did some great clean up.

What next
Full on Mudding and Taping should be complete early next week and off to priming.
We now have the siding on site, trims and corners are started and siding is going on paint colours are picked and will be ordered tomorrow.

Still Needed
The finish paint is to be ordered. The window returns material and trim will be brought on site.  The door jambs will be picked up next week.

Volunteers
Many people have come together to keep this project moving forward, many thanks to
you all.  Some more people in the finish carpentry area would be helpful.

Further down the road
The siding team will get started with trims and mouldings.
The flooring is on site and anxiously awaiting the painting to be done.
Doors will be ordered and Frame (jamb) material picked up.


Materials/Tools
The drywall lift for ceilings has been returned. All tools required are on site.

Food and Drink
As per drywall schedule.
Many thanx to our food teams, especially to Mary Grey of Gravenhurst, who continues to
go beyond all expectations.

Inspections
We are all up to date.

My thoughts
A huge thank you to all of you for your continued dedication to this worthy project, especially Larry Fernly who comes every day and has made this project his own. Dorothy and Marj, who have come weekly since the beginning. Thank you Darren, from Muskoka Exteriors.