Thursday, November 10, 2011

Drywall


Daily Log November 8, 2011
Who was on site
Larry, Fred, Norm, Bill, Mike, Dorothy, Doug, Emily and Vince
What Happened
The drywall is progressing well, the boarding is nearing completion and full taping is under way.
One of our hot water tanks was replaced.

What next
A bit more and the main floor will be boarded completely, the taping is progressing well, thank you Jesse for continuing the taping and mudding clinic. Sound proofing of the fire/party wall between units, we have tracked down the illusive “party wall” sound proof insulation, it’s going in Tuesday,. Yay Done and we await
Wednesdays inspection
Still Needed
Kitchen colours/shades, counter tops, Paint colours and trim.
Volunteers
Many people have come together to keep this project moving forward, many thanks to
you all. Currently we have who we need for drywall boarding. Some more expertise
would be helpful with the taping and mudding of the drywall. Thank you volunteers for
today’s d.wall moving extravaganza
Further down the roadThe siding team will get started as soon as the illusive siding colour is available
The cement pads can be poured outside, two now done two to go
Materials/Tools
The drywall lift for ceilings has been returned. All tools required are on site
Food and Drink
As per drywall schedule
Many thanx to our food teams. Especially to Mary Grey of Gravenhurst who continues
to go beyond all expectations
Inspections
We are all up to date. Next week with some shipping luck we can have the sound
proofing in our fire/separation wall inspected and no longer be able to pass through from
side to side without using a door
My thoughts
We have graduated to the walls with the drywall. Thank you to all who helped to
complete the ceiling board, not an easy task. Go team *** Jesse is awesome at taping
and teaching some tricks to our team of skilled regular volunteers

No comments: