Monday, November 21, 2011

Daily Log November 21, 2011


Who was on site
Larry, Fred, Doug, Emily and Vince (Project Manager)

What Happened
The drywall taping is progressing well, with careful expectations of completion (main floor) this week.

What next
Full on Mudding and Taping should be complete this week and off to priming. The siding shipment has been a little slow in arriving, due to the company’s volume of sales this season. We now have the basics of siding on site, trims and corners can get started.

Still Needed
The primer through Home Depot, shall be picked up early this week.

Volunteers
Many people have come together to keep this project moving forward, many thanks to you all.  Some more expertise would be helpful with the taping and mudding of the drywall. With some luck we will have Jesse back for extreme taping and mudding.

Further down the road
The siding team will get started with trims and mouldings.


Materials/Tools
The drywall lift for ceilings has been returned. All tools required are on site.

Food and Drink
As per drywall schedule
Many thanx to our food teams. Especially to Mary Grey of Gravenhurst who continues to go beyond all expectations.

Inspections
We are all up to date.

My thoughts
Thank you to all who helped to complete the boarding. We are well on our way through
the mudding and taping process. Though some professional help would be great.