Monday, August 1, 2011

What holiday?

DAILY  LOG August 1, 2011

Who Was On-Site?
Larry, Dave, Brian, Dave, Ike, DougP, Michael O’Grady (Project Manager)

What Happened?
DougP sorted out boots and hard hats. Brian et al worked on the blocks.

What Next?
Tuesday, August 2 – The Corrections Canada Crew is coming out for a hardy day’s work of installing the engineered floor joist system.
Wednesday, August 3 – Friday, August 5 –We will have resumed framing of the main structure.
Jesse Campbell of Jesse Campbell Construction has volunteered to bring in his crew and install the truss
roof system.

IN TWO WEEKS: Monday, August 8 – Friday, August 12
Gravenhurst Plumbing and Greenside Electric will do the plumbing, electrical and heating rough-ins.
Bill Gee of Great Northern Insulation has volunteered to provide us the labour to install the insulation
which he will provide at cost. He will also provide the truck to blow in the attack insulation once the
drywall is installed.

IN THREE WEEKS: Monday, August 14 – Friday, August 19
Drywall installation
VolunteersTuesday, August 2 – Corrections Canada is providing 13 Volunteers + Larry + Emma + Derek + DougP +
MikeO
Wednesday, August 3 -- 8 Volunteers + DougP + MikeO
Thursday, August 4 -- 8 Volunteers + DougP + MikeO
Friday, August 5 -- 8 Volunteers + DougP + MikeO
Monday, August 8 – Friday, August 12
8 Volunteers per day to complete framing and do site clean up
Monday, August 14 – Friday, August 19
It does not seem likely the big company crews come out to do drywall installation. (They are booked for
later dates.) ERGO:
8 Volunteers per day for Drywall installation

Materials/Tools?
Monday, July25 – Friday, August 5
Engineered Floor System, wall framing materials, Roof Truss system, SM Foam, skill saw, hammers,
levels, squares, tape measures, tool belts, ladders, roof shingles
Engineered Floor system from Chamberlain’s Tim-Br-Mart (at a nicely reduced cost)
Windows and doors from Muskoka Windows and Doors.
Monday, August 8 – Friday, August 12
Brooms, dust masks and garbage bags
Monday, August 14 – Friday, August 19
Drywall materials, drywall nails and screws, drywall lifter, dust masks, box-cutter knives

Food and Drink
Many thanks to Oliver’s Coffee of Gravenhurst for providing us with their delicious coffee and muffins.Tuesday, August 2 – Food and Drink Required for 18
Wednesday, August 3 – Friday, August 5 – Food and Drink Required for 10 each day
  Be sure and call 644-3138 around 8:30 a.m. for a final head count.

Inspections
For framing
For plumbing, electrical and heating rough-ins
For insulation and vapour barrier
For occupancy and final

My Thoughts
I think concrete blocks are like 2x4 studs. No matter how many you order you always run out. Anyway, we got 519 all ready to go for tomorrow. It looks like another beautiful, but hot, day. Our prep work is done. We are ready to roll.
Many thanks to all those who volunteered and made this a reality.

Mike O'Grady
Construction Project Manager
HABITAT FOR HUMANITY
1964 Muskoka Beach Road
RR 1 Gravenhurst ON P1P 1R1
705-646-0106 Ext 204
mike@habitatmuskoka.com www.habitatmuskoka.com