Tuesday, July 19, 2011

Stones, beaches, tar


DAILY  LOG JULY 19, 2011

Who Was On-Site?
Arlene, Paul, Fred, DougP, Michael O’Grady (Project Manager)

What Happened?
Arlene, Paul and Fred rolled the tar on the foundation walls. (Brian’s machine went kapooie.) We laid out the O-Pipe, cleaned up the site, ate a wonderful lunch, and called it a day.

What Next?
Wednesday, July 20 – Friday, July 22
Wednesday – Apply SM Foam and Dimple Wrap
Thursday – Fred from Brent Quarries will come first thing in the morning and sling the stones over the OPipe. I have called for a late morning inspection. Once the inspection is passed, hit the beach. (I hope them Greenpeace guys don’t show up and try and push me back into the water.)
Friday -- Backfill

Monday, July25 – Friday, July 29
The framing of the floor joist system should be underway and finished by Friday, July 29.
Monday, August 1 – Friday, August 5
Framing of the main structure.  Jesse Campbell of Jesse Campbell Construction has volunteered to bring
in his crew and install the truss roof system
Monday, August 8 – Friday, August 12
Gravenhurst Plumbing and Greenside Electric will do the plumbing, electrical and heating rough-ins. Bill Gee of Great Northern Insulation has volunteered to provide us the insulation materials at cost and
the labour for free. He will also provide the truck to blow in the attack insulation once the drywall is
installed.
Monday, August 14 – Friday, August 19
Drywall installation

Volunteers
Wednesday, July 20 – Friday, July 22
Wednesday -- 4 Volunteers + DougP + MikeO = TOTAL OF 6
Thursday – NO VOLUNTEERS
Friday – 4 volunteers + 4 tradesmen + DougP + MikeO = TOTAL OF 10
Site Supervisors needed
Monday, July25 – Friday, July 29
5 -6 Volunteers per day with framing experience
Site Supervisors needed
Monday, August 1 – Friday, August 5
We are hoping to have the big company crews come out for the framing
Site Supervisors needed
Monday, August 8 – Friday, August 12
2 Volunteers per day needed to do site clean up
Site Supervisors needed
Monday, August 14 – Friday, August 19
We are hoping to have the big company crews come out to do drywall installation
Site Supervisors needed

Materials/Tools?
Wednesday, July 20 – Friday, July 22
SM Foam, O-Pipe, Dimple Wrap, 1” stone, backfill, box-cutter knives, hammer drill, tap-con screws,
wheel barrow, shovels, rakes.

Monday, July25 – Friday, August 5
Engineered Floor System, wall framing materials, Roof Truss system, SM Foam, skill saw, hammers,
levels, squares, tape measures, tool belts, ladders, roof shingles.
Windows and doors from Muskoka Windows and Doors.

Monday, August 8 – Friday, August 12
Brooms, dust masks and garbage bags

Monday, August 14 – Friday, August 19
Drywall materials, drywall nails and screws, drywall lifter, dust masks, box-cutter knives

Food and Drink

Wednesday, July 20 – FOOD AND DRINK FOR 6
Thursday, July 21 – NO FOOD AND DRINK REQUIRED
Friday, July 22 – FOOD AND DRINK FOR 10
  Be sure and call 644-3138 around 10:30 a.m. for a final head count.

Inspections

  • For weeping tiles, drainage stones, and weather-proofing on the exterior of the foundation walls.
  • For framing
  • For plumbing, electrical and heating rough-ins
  • For insulation and vapour barrierFor occupancy and final.

My Thoughts
I heard that Thursday was going to be 43˚C!!!!!!!!!!!!!!!!!
Double Ouch.

Mike O'Grady
Construction Project Manager
HABITAT FOR HUMANITY
1964 Muskoka Beach Road
RR 1 Gravenhurst ON P1P 1R1
705-646-0106 Ext 204
mike@habitatmuskoka.com www.habitatmuskoka.com

No comments: