DAILY  LOG JULY 25, 2011

Who Was On-Site?
Susan, Kevin, Larry, Fred, DougP, Michael O’Grady (Project Manager)

What Happened?
We got the sill gasket and the sill plates on, and we got rained out. Thanks to everybody for showing up
and making a good start on the walls.

What Next?
Monday, July25 – Friday, July 29
The framing of the floor joist system should be underway and finished by Friday, July 29.
Monday, August 1 – Friday, August 5
Framing of the main structure.  Jesse Campbell of Jesse Campbell Construction has volunteered to bring
in his crew and install the truss roof system
Monday, August 8 – Friday, August 12
Gravenhurst Plumbing and Greenside Electric will do the plumbing, electrical and heating rough-ins.
Bill Gee of Great Northern Insulation has volunteered to provide us the labour to install the insulation
which we will provide. He will also provide the truck to blow in the attack insulation once the drywall is
installed.
Monday, August 14 – Friday, August 19
Drywall installation

Volunteers
Monday, July25 – Friday, July 29
5 -6 Volunteers per day
Site Supervisors needed
Monday, August 1 – Friday, August 5
We are hoping to have the big company crews come out for the framing
Site Supervisors needed
Monday, August 8 – Friday, August 12
2 Volunteers per day needed to do site clean up
Site Supervisors needed
Monday, August 14 – Friday, August 19
We are hoping to have the big company crews come out to do drywall installation
Site Supervisors needed

Materials/Tools?
Monday, July25 – Friday, August 5
Engineered Floor System, wall framing materials, Roof Truss system, SM Foam, skill saw, hammers,
levels, squares, tape measures, tool belts, ladders, roof shingles
Engineered Floor system from Chamberlain’s Tim-Br-Mart (at a nicely reduced cost)
Windows and doors from Muskoka Windows and Doors.
Monday, August 8 – Friday, August 12
Brooms, dust masks and garbage bags
Monday, August 14 – Friday, August 19
Drywall materials, drywall nails and screws, drywall lifter, dust masks, box-cutter knives

Food and Drink
Many thanks to the Catholic Women's League ladies of Saint Paul’s Parish in Gravenhurst for providing us with a most excellent lunch on Friday.
Monday, July25 – Friday, July 29
FOOD AND DRINK FOR 10 EVERY DAY
  Be sure and call 644-3138 around 8:30 a.m. for a final head count.

Inspections

  • For framing
  • For plumbing, electrical and heating rough-ins
  • For insulation and vapour barrier
  • For occupancy and final

My Thoughts
We have a plan in place to fix the bowed wall. It will require some re-bar and some concrete and a short,
but hard, day’s work from our many willing and generous Volunteers. Once again, thanks to all for their hard work and willingness.

Mike O'Grady
Construction Project Manager
HABITAT FOR HUMANITY
1964 Muskoka Beach Road
RR 1 Gravenhurst ON P1P 1R1
705-646-0106 Ext 204
mike @ habitatmuskoka.com www.habitatmuskoka.com

No comments: