Thursday, July 21, 2011


DAILY  LOG JULY 20, 2011

Who Was On-Site?
Arlene, Bill, Larry, DougP, Michael O’Grady (Project Manager)

What Happened?
Arlene, Bill, Larry and Doug installed the SM Foam. Larry and I installed the Dimple Wrap.

What Next?
Thursday, July 21 – Friday, July 22
Thursday – Fred from Brent Quarries will come first thing in the morning and sling the stones over the OPipe. I have called for a late morning inspection. Once the inspection is passed, hit the beach. (I hope them Greenpeace guys don’t show up and try and push me back into the water.)
Friday -- Backfill
Monday, July25 – Friday, July 29
The framing of the floor joist system should be underway and finished by Friday, July 29.
Monday, August 1 – Friday, August 5
Framing of the main structure.  Jesse Campbell of Jesse Campbell Construction has volunteered to bring
in his crew and install the truss roof system
Monday, August 8 – Friday, August 12
Gravenhurst Plumbing and Greenside Electric will do the plumbing, electrical and heating rough-ins.
Bill Gee of Great Northern Insulation has volunteered to provide us the insulation materials at cost and
the labour for free. He will also provide the truck to blow in the attack insulation once the drywall is
installed.
Monday, August 14 – Friday, August 19
Drywall installation

Volunteers
Thursday, July 21 – Friday, July 22
Thursday – 4 VOLUNTEERS
Friday – 4 volunteers + 4 tradesmen + DougP + MikeO = TOTAL OF 10
Site Supervisors needed
Monday, July25 – Friday, July 29
5 -6 Volunteers per day with framing experience
Site Supervisors needed
Monday, August 1 – Friday, August 5
We are hoping to have the big company crews come out for the framing
Site Supervisors needed
Monday, August 8 – Friday, August 12
2 Volunteers per day needed to do site clean up
Site Supervisors needed
Monday, August 14 – Friday, August 19
We are hoping to have the big company crews come out to do drywall installation
Site Supervisors needed

Materials/Tools?
Thursday, July 21 – Friday, July 22
1” stone, backfill, box-cutter knives, hammer drill, tap-con screws, wheel barrow, shovels, rakes
Monday, July 25 – Friday, August 5
Engineered Floor System, wall framing materials, Roof Truss system, SM Foam, skill saw, hammers,
levels, squares, tape measures, tool belts, ladders, roof shingles
Windows and doors from Muskoka Windows and Doors.
Monday, August 8 – Friday, August 12
Brooms, dust masks and garbage bags
Monday, August 14 – Friday, August 19
Drywall materials, drywall nails and screws, drywall lifter, dust masks, box-cutter knives

Food and Drink

Wednesday, July 20 – FOOD AND DRINK FOR 6
Thursday, July 21 – NO FOOD AND DRINK REQUIRED
Friday, July 22 – FOOD AND DRINK FOR 10
  Be sure and call 644-3138 around 8:30 a.m. for a final head count.

Inspections

  • For weeping tiles, drainage stones, and weather-proofing on the exterior of the foundation walls.
  • For framing
  • For plumbing, electrical and heating rough-ins
  • For insulation and vapour barrier
  • For occupancy and final


My Thoughts
All of the volunteers are great, and every so often a shining star appears. Such is the case with Larry
Fernley. It was a hot horrible day down in the hole. Larry was drenched and tired. I told him without
the Dimple Wrap I would have to call off the stoneslinger and the inspection and the backfill. “Well,”
says Larry. “Then let's do it.” And he stayed and we got the Dimple Wrap installed.

The efforts of all our wonderful volunteers got us this far, and without their hard work and dedication
we would not even have been considering installing the Dimple Wrap. But when that last push was
needed, and Larry was the last man on the job, he stayed and got 'er done.
And, so, as the old song goes: “Hats off to Larry!”

And hats off to each and every volunteer for working so hard to keep us on schedule.