SITE SUPERVISOR : HOWARD RUTTAN

VOLUNTEERS: NAN ALLEN, BEB TILLSON, ROB ABBOTT, DOUG PATTERSON, ROB'S FRIENDS: DON AND PETER, WILLY FLETCHER.
                     BEAVER CREEK CREW OF 5
                     RESTORE CREW 


CONTRACTORS: A.D.A.M. ELECTRIC. ALL ELECTRICAL WORK WAS COMPLETED IN BOTH UNITS TODAY.
                         HPN PLUMBING. ALL PLUMBING WORK WAS COMPLETED IN BOTH UNITS TODAY.
                         WESTERBY SIDING. SIDING WAS COMPLETED TO THE POINT OF A SMALL AREA WHERE IT INTERFACES WITH THE INCOMPLETE STEEL ROOF.

ACTIVITIES


  • THE ROOF IS TO BE COMPLETED NEXT WEDNESDAY. AT THAT TIME WESTERBY WILL BE COMPLETING THE REMAINING SIDING AS WELL. HOWEVER THIS SHOULD NOT HAVE AN IMPACT ON THE FINAL INSPECTION SINCE THAT IS NOT A STRUCTURAL OR CODE VIOLATION. I GUESS WE'LL FIND OUT WHEN FINAL IS DONE.
  • DEB HAS COMPLETED TOUCH-UP PAINTING AND REPAIRING WALLS AND CEILING IN 1014A.
  • WILLIE MUDDED AND SANDED DAMAGED WALLS. ALSO CUT ONE OF THE CABINETS TO PROPER 12 INCH SIZE.
  • DOUG INSTALLED STAIR HANDRAILS.
  • RESTORE AND BEAVERCREEK CREW  DELIVERED FRIDGES, STOVES AND WASHER DRYERS FOR BOTH UNITS
  • EVERYONE ASSISTED MOVING NEW APPLIANCES INTO RESPECTIVE UNITS. AS WELL TRUCK WAS LOADED WITH ALL TOOLS AND EQUIPMENT THAT WAS ON SITE FOR THE BUILD AND RETURNED TO THE BUILD ROOM.
  • VARIOUS ITEMS REPAIRED AND INSTALLED.

NEXT: 


  • SCHEDULED INSPECTION FOR TOMORROW.
  • ROOF AND SIDING COMPLETION NEXT WEDNESDAY.
  • COMPLETE PAINTING TOUCH UPS IN 1014.
  • COMPLETE VARIOUS INSTALLATION ITEMS SUCH AS  DRYER VENT PIPES, ETC.
  • TAKE TRAILER IN TO LOAD GARBAGE FOR DUMP RUN.
  • SCHEDULE CLEAN-UP CREW FOR FINAL CLEAN-UP ON  MONDAY. 
~HOWARD RUTTAN  