Daily Log Patty Parsons Project Dec. 16


Site supervisor: Howard Ruttan

Volunteers: Rob Abbott, Doug Patterson, Mike Guiry, Deb Tillson 

Contractors: Buttler Heating

Activities: Deb organizing the basement tool room. 
               Rob, Doug, Mike and Howard working on decks and steps. 

              Two sets of stairs completed. 
               Ramp and remaining steps 80% done.

Buttler Heating completed HRV in 1014A. Continued working on HRV in 1014.

Next: Kitchen in 1014A to be installed tomorrow.
                   Continue with stairs and decks.
                    Schedule remainder of roof install.

~Howard Ruttan