Saturday, December 4, 2010

The birth is nigh

Daily Logs for Dec. 3/4 Patty Parsons Project


VOLUNTEERS; SITE SUPERVISOR HOWARD RUTTAN, ROB ABBOT, DOUG PATTERSON, MRS PATTERSON, JAN TURNER, DEB TILSON, CODY FLETCHER, WILLIE FLETCHER,  KEN WETTLAUFER, DAVE  MURPHY.

CONTRACTORS: A.D.A.M. ELECTRIC, VINCENT ROOFING, WESTERBY SIDING, BEDROCK LANDSCAPE.
 

ACTIVITIES
  • WESTERBY INSTALLING SOFFITTS IN BOTH PORCHES.  
  • VINCENT INSTALLING ROOFING ON 1014.
  •  A.D.A.M. COMPLETING INSTALLATION OF  ELECTRICAL FIXTURES ON MAIN FLOOR IN BOTH UNITS. 
  • VOLUNTEERS MOVING ALL MATERIAL AND TOOLS TO BASEMENTS OF BOTH UNITS.
  • CLEANING WALLS AND FLOORS IN BOTH UNITS.
  • DAVE AND KEN INSTALLING TRIM AND CAULKING IN BOTH UNITS.
  • ICKING UP TRAILER LOAD OF WOOD CHIPS AND SPREADING ON GRANITE FILL TO MINIMIZE TRACKING DIRT INTO HOUSES ON SUNDAY.
  • BEDROCK GRADED FILL ALONG SIDE OF HOUSES AND PLOWED SNOW AWAY FROM FRONT AND SIDE OF HOUSES.    
NOTE: HOUSES ARE NOW PREPARED FOR DEDICATION CEREMONIES ON SUNDAY. BE AWARE: ALL CONSTRUCTION AND FINISHING IS NOT COMPLETED! 

OUTLINE OF CURRENT STATUS OF CONSTRUCTION ACTIVITIES:

 THIS IS MY CURRENT RECOLLECTION AND IF i'VE MISSED SOME ITEM  I WILL STAND
CORRECTED. BUT IT IS ESSENTIALLY COMPLETE AND I FEEL MAY BE USEFUL TO GIVE EVERYONE AN OUTLINE OF WHERE WE STAND IN OBTAINING A FINAL INSPECTION AND OCCUPANCY PERMIT. 

FINAL INSPECTION AND PERMIT REQUIREMENTS: 

  • COMPLETE SIDING INSTALLATION INCLUDING FACIA WHICH WILL FOLLOW COMPLETED  ROOFING INSTALLATION - CONTRACTOR
  • COMPLETE ROOFING INSTALL. THIS IS UNCERTAIN DUE TO BACK-ORDERED MATERIAL FROM USA. - CONTRACTOR
  • COMPLETE CONSTRUCTION OF 3 ENTRY  STEPS AND RAMP TO DISABLED SIDE.- VOLUNTEER/CONTRACTOR
  • COMPLETE FILL AND GRADING ALONG SIDE OF BOTH UNITS TO REAR OF SIDE ENTRY DOORS.- CONTRACTOR
  • COMPLETE FRAMING AND DRYWALLING AROUND FURNACE PIPING IN CLOSETS.- VOLUNTEERS
  • INSTALL HRV'S AND DUCTING REQUIRED.- CONTRACTOR
  • OBTAIN AND INSTALL KITCHEN CABINETS.- CONTRACTOR
  • INSTALL COUNTER TOPS.- CONTRACTOR
  • INSTALL PLUMBING FIXTURES, ABS AND PRESSURE LINES  BOTH UNITS - CONTRACTOR
  • COMPLETE ELECTRICAL INSTALLS IN BASEMENTS.- CONTRACTOR
  • CALL FOR INSPECTION. VOLUNTEERS

ITEMS TO BE FINISHED BUT NOT REQUIRED FOR FINAL: ( ALL VOLUNTEER JOBS)

  • MUD BASEMENT STAIRS WALLS AND ELECTRICAL BOX WALLS IN BOTH UNITS
  • FILL DAMAGE AND TOUCH-UP PAINTING IN ALL AREAS.
  • COMPLETE CLOSET HANGER INSTALLS.
  • INSTALL BATH ROOM DOOR LOCK...1014
  • RETURN ALL MATERIAL AND TOOLS TO STORAGE ROOM.
  • FINAL CLEAN-UP
  • EXIT!!
          
VOLUNTEERS REQUIRED: AS POINTED OUT ABOVE STARTING MONDAY WE NEED 4 TO 6 SKILLED VOLUNTEERS EVERY DAY. I BELIEVE WE CAN COMFORTABLY COMPLETE ALL OUR (VOLUNTEER)  TASKS BEFORE  CHRISTMAS IF WE HAVE THE PEOPLE.

~HOWARD RUTTAN

No comments: