Tuesday, November 16, 2010

They're just floored

Daily Log, November 16th, 2010
VOLUNTEERS: SITE SUPER HOWARD RUTTAN, NAN ALLEN, TONI GREEN, MAVIS, JEAN, MARY, DOUG.

CONTRACTORS: LAWRENCE SEEHAVER CONTRACTING.
                    
ACTIVITIES: SEEHAVER CONTRACTING WERE PARGING ALL DAY. TOBIN CEMENT DELIVERED ADDITIONAL PARG PREMIX.
                   TONI AND CREW PAINTED UP A STORM IN 1014. 
                   BELL SUB CONTACTORS REMOVED POLE FROM FRONT OF LOT. GOOD WORK JANE!!
                   I CONTACTED WESTERBY SIDING AND VINCENT ROOFING AND GOT COMMITTMENTS FOR INSTALLATIONS.
                   I CONTACTED BUILDING INSPECTOR TO DETERMINE STATUS OF PLUMBING INSPECTION. 
                   TALKED TO BRADLEY CONTRACTING TO CONFIRM SITE TIME TOMORROW FOR TRIM WORK.
                   VARIOUS TRIM, PAINTING AND WORK DISCUSSIONS WITH VOLUNTEERS.

NEXT: COMPLETE PARGING ON THURSDAY.
          TRIM, PAINT CLEAN UP FOR WEEKEND FLOORING INSTALL.

NOTE: AS IT STANDS NOW WE WILL  NOT BE NEEDING VOLUNTEERS FOR SATURDAY, SUNDAY, AND MONDAY SINCE FLOORING INSTALLERS WILL BE MOVING BACK AND FORTH BETWEEN BOTH UNITS TO INSTALL FLOORING BY TYPE AND IN SEQUENCE IN EACH UNIT. i WILL BE IN AND OUT TO CHECK ON INSTALL DURING THE 3 DAYS.

~HOWARD RUTTAN