Tuesday, November 23, 2010

Siding and roofing, porching, posting

Daily Log: Patty Parsons Project November 23, 2010


VOLUNTEERS
  • SITE SUPERVISOR HOWARD RUTTAN
  • NAN ALLEN, DOUG PATTERSON, SUSAN HEMMING, PETER HEMMING CAROL DONALDSON, TONI GREEN (BRIEFLY).
  • JEREMY MCMEEKIN (AKZO NOBEL) AND DAVE DAMIGNANI ( AKZO NOBEL) THESE TWO GENTLEMEN WERE FROM THE COMPANY THAT SUPPLIED THE PAINT, WHICH INCLUDES MANY BRAND SUCH AS CIL WHICH  WE ARE USING. 
  • CHARLIE AND LINDA (SORRY, I DON'T HAVE THE LAST NAME) WHO ARE INSTALLING THE FLOORING.


CONTRACTORS


  • HARRY WESTERBY TO DROP OFF THE VINYL SIDING. HE WILL BE RETURNING THURSDAY TO INSTALL THROUGH THE WEEKEND.

ACTIVITIES:




  •  SUSAN, CAROL, JEREMY AND DAVE FILLED AND PAINTED UP A STORM. 
  • DOUG MADE A RUN TO THE TRANSFER  STATION AND DOUG AND PETER RETURNED THE SCAFFOLDING THE REMAINED ON SITE.
  • PETER FINISHED TRIM IN THE BEDROOMS OF 1014. HE PAINTED PORCH POSTS. AND OTHER STUFF.
  • DOUG WAS CLEANING UP THE YARD. SNAPPING CHALK LINES ON THE WALL FOR FILL LEVEL.
  • FLOORING SHOULD BE COMPLETE TODAY IN 1014A.

NEXT


  • INSTALL FLOORING IN 1014. THIS WILL PROBALY CONTINUE THROUGH SATURDAY.
  • PAINT, TRIM, PAINT, TRIM,PAINT TRIM, IN 1014A. 
  • CLEAN UP BOTH UNITS....SWEEP VACUUM.
  • INSTALL PORCH POSTS PRIOR TO SOFFIT INSTALL.
  • ASSEMBLE SLIDING DOOR FRAMES AND INSERTS.
  • DRYWALL MUDDING
  • INSTALL SIDING STARTING THURSDAY.
  • INSTALL ROOFING STARTING FRIDAY. ONLY HALF THE ROOFING AVAILABLE. BACKORDER FROM USA.

NEED LOTS OF PEOPLE!

~HOWARD RUTTAN