Wednesday, November 10, 2010

Pours and floors, locks and flocks, soil and toil

Daily Log: Patty Parsons Build, Report: Monday/Tuesday, November 8/9


VOLUNTEERS
SITE SUPERVISOR HOWARD RUTTAN
NAN ALLEN, BILL NEISS,SUE WOODS, DOUG PATTERSON, JIM PARTRIDGE, JEAN __ , MIKE GUERY.

CONTRACTORS:


  •  STEVE BYNO DROPPED BY TO DISCUSS PORCH . HE AGREED TO GET IN THIS WEEK AND COMPLETE THE PORCH POUR.  
  •  BUTTLER HEATING, STEVE AND JIM, WERE IN AND COMPLETED THE TANK HOOK UP AND THE INLET AND BREATHER PIPES. THEY WILL BE IN TODAY TO INSTALL THE FURNACE PIPE.
  •  IAN WALLACE (VOLUNTEER) WAS IN TO DISCUSS TRIM INSTALL. EXCEPT FOR WINDOW TRIM THE REMAINDER IS BEING  HELD UP TILL THE FLOORS ARE IN.  

ACTIVITIES


  • JEAN, SUE AND ( THE VOLUNTEER'S NAME ESCAPES ME) PAINTED TRIM ALL DAY UNDER JIM'S HELP AND ASSISTANCE. 
  • MIKE AND DOUG ASSISTED WITH CLEAN-UP AND TAKING TRAILER OF TRASH TO THE DUMP. THEY ALSO TRAILERED THE FENCING BACK TO PRO-LINE. AFTER THAT THEY STARTED INSTALLING WINDOW TRIM.           
I WAS AWAY YESTERDAY AT A FUNERAL AND JIM PARTRIDGE AGREED TO STEP IN. THE VOLUNTEERS INSTALLED THE LOCKS ON THE FRONT DOORS AND CONTINUED PAINTING TRIM AND BEDROOM WALLS IN 1014A.

NEXT


  • POUR FRONT PORCHES: SOLID CONCRETE CONSTRUCTION
  • PARGE BASEMENT WALLS; SEEHAVER CEMENT CONTRACTING
  • STEEL ROOF INSTALL: VINCENT ROOFING. THE STEEL IS ALREADY ON SITE.
  •  I TALKED TO RON BRENT AND AND HE IS READY TO DELIVER SOIL, GRANIT SCREENING AND 3/4 STONE WHEN WE ARE READY. THIS WILL HAPPEN IMMEDIATELY THE PARGING IS COMPLETE AND EITHER BEFORE OR AFTER SIDING TO ACCOMODATE SCAFFOLDING MOVEMENT.
  • VINYL SIDING INSTALL: HARRY WESTERBY SIDING.
  • CONTINUE WINDOW TRIM INSTALL AND PAINTING. 
  • FOLLOW-UP ON FLOORING SELECTION AND DELIVERY AND HYDRO POLE REMOVAL.
  • Early on in the process
  • COMPLETE MUDDING ON 1014....PROBABLY FRIDAY. 

~HOWARD RUTTAN