Friday, November 5, 2010

Mudding, parging, pourch pouring

November 4 report
Patty Parsons Project build in Bala
VOLUNTEERS:
SIGHT SUPERVISOR HOWARD RUTTAN
                     NAN ALLEN, TONI GREEN, DEB TILLSON,

CONTRACTORS:

  • MIKE FROM DAN GOFORTH CONTRACTING
  • MIKE CONTINUED WITH MUDDING THE DRYWALL ON 1014.


ACTIVITIES:

  • TONI AND DEB PAINTED THE SECOND COAT ON THE HOUSE EXCEPT THE 2 BEDROOMs: COLORS ARE NOT AVAILABLE.
  • WE WRAPPED WORK UP ABOUT 4 PM
  • MIKE ANTICIPATES FINISHING MUDDING 1014 MID WEEK NEXT WEEK.
  • SUMP PUMP INSTALLED IN 1014A YESTERDAY.


NEXT:   

  • WE NEED THE KITCHEN CUPBOARDS FOR 1014A  ASAP. 
  • COMPLETE DRYWALL.
  • TRIM WINDOWS ON 1014A 
  • PAINT TRIM THAT WE HAVE ALTHOUGH THIS IS A SMALL AMOUNT OF OUR NEEDS.
  • IT APPEARS HUNTING SEASON STARTING THIS WEEK AND THE CONTRACTORS INVOLVED WITH COTTAGE CLOSINGS (HPN, MARTINO, BUTTLER) ARE
  • ESSENTIALLY UNAVAILABLE. WEATHER NEXT WEEK LOOKS MODERATE AT THIS TIME...LETS HOPE IT IS THAT WAY.
  • WE HAVE SOME CLEANUP TO DO AND SOME SMALL JOBS BUT WITH PAINTING DONE ON 1014A WE ARE NOW WAITING FOR MUDDING COMPLETION, PARGING.
  • AND PORCH POUR. 


~HOWARD RUTTAN