Saturday, November 6, 2010

More muddy dry walls



Patty Parsons Project
Daily log, Oct. 28th, 2010
SITE SUPERVISOR: HOWARD RUTTAN

VOLUNTEERS: MIKE GUERY, WILLY FLETCHER, DOUG, BOB MCTAVISH, JAN

ACTIVITIES:  
  • ALL DRYWALL BOARDING IN BOTH UNITS IS NOW COMPLETED INCLUDING THE WINDOW FRAMES IN 1014. 
  • TOOK A LOAD TO THE TRANSFER STATION OF ALL CUT-OFFS AND SCRAP LUMBER. 
  • RETURNED ALL TOOLS TO THE BASEMENT AND CLEARED AND SWEPT MAIN FLOOR, READY FOR MUDDING.
  • DAN GOFORTH SENDING IN A SECOND DRYWALLER TOMORROW TO ASSIST BOB JUKES IN MUDDING SECOND UNIT.
  • ATTIC ACCESS PORT MODIFIED FOR 1014 TO LESSEN WEIGHT. 
  • "OCEAN CAN" PICKED UP AND RETURNED TO CRS. OUTHOUSE "REFRESHED".

CONTRACTORS: BOB JUKES COMPLETING THIRD COAT OF MUDDING AND SANDING ON 1014A.
                        
NEXT
  • INSTALL LATHE ON BASEMENT EXTERIOR WALL READY FOR PARGING. CLEAN-UP OUTSIDE. POUR BASEMENT STEP AND PORCH. INSTALL SIDING.MUD 1014
  •   LOOK FOR TASKS FOR 6 VOLUNTEERS FROM BEAVER CREEK FOR THURSDAY, FRIDAY
  • CONTACT WESTERBY SIDING
NOTE: PRIMER PAINTING OF 1014A WILL COMMENCE MONDAY.

VOLUNTEERS NEEDED:

FRANKLY, WE ARE RUNNING OUT OF JOBS TO GIVE PEOPLE FOR THE MOMENT (ONLY). THE MUDDING IS UNDERWAY IN BOTH UNITS AND EXCEPT FOR SOME SMALL JOBS WE HAVE TO WAIT FOR THE MUDDING AND PARGING TO BE DONE AT WHICH TIME WE WILL AGAIN BE BUSY.

I WILL MAKE A DECISION TOMORROW ON THE NEED FOR BEAVER CREEK FOLKS ON FRIDAY. ALSO ROB, WE WILL HAVE TO TOUCH BASE TOMORROW ABOUT SATURDAY.

~HOWARD