Construction Daily Log: Parry Parsons Build

Date: October 8, 2010

Rob Abbott reporting 

Photos from Frank's Blackberry! 
(Thanks, Frank. It's great to see what it looks like inside! / Jenn)


On Site:
Site Supervisor: Frank Fraser

Volunteers: Peter the Great, Mitch and the 3 Robs: Myself, Mike Robbins, and Roberta. Nan was back and forth all day.

Contractors: ADAM Electric installed the meter base.

Visitors: Lots: Ellen, Howard, Angel and Connie stopped by.

Daily Log: Another spectacular day was spent inside doing drywall. We broke into 2 teams: Frank Mitch, and Peter worked on drywalling the walls of 1014A. 

Meanwhile, the three Knobs, er I mean Robs, worked on the ceiling of 1014. 


Ellen brought a cake for Frank to commemorate his second last day. By 3:00 there were no more volunteers, so Frank was left to wait in case contractors showed up.

We said goodbye, to Mike Robbins, who has been a regular, volunteering at site about 3 days per week, all summer. He's heading back to his home in Rossland BC. 
Bye Mike and thanks.


Action/Follow-Up Items:
Start deciding on flooring
Get contractor to do eave
Get tapers

Next Days/Week Plan:
Saturday – Drywall Frank's Last Day!
Tuesday – Thursday Drywall and Outside
Thursday – Clean up site for possible tours during Cranberry Festival
Friday – Saturday – Closed, except for tours during festival

Volunteer Requirements: We have work for a large crew. Lots of jobs.
 