Rob Abbott reporting

On Site:  
Site Supervisor: Howard Ruttan
Volunteers:  Deb, Jim P., Mike G, Peter - The Great, and, for a few hours only, Rob - The Mediocre.  As usual, Brian McD and Nan got us started and checked on us throughout the day.
Contractors: Bob Duke

Daily Log: The crew got bored with wall board; most of 1014 is done and the corner bead got started.  The Duke of Drywall, Bob, got another coat on all the seams of 1014A.   The office trailer got removed to be put in storage for the winter. These laconic sentences belie the significant progress made today.

Action/Follow-Up Items:
Howard: Parger, Front porches, Siding, Plumbers (so we can drywall, run vent through roof, and hook-up sump pumps.
Rob: Porch slab insulation, Arrange for ReStore truck, pick up HRV units
Jane:  light fixtures (Needco, or Home Hardware Pt. Carling), toilets and sinks, paint/primer (GIK), blinds (GIK).

Next Days/Week Plan:
Saturday Drywall 1014, Start moving tools and materials needed for completion out of container and into one of the units.
Monday – Clear out container.

Volunteer Requirements:   We have work for a large crew.  Lots of jobs.

Materials/Tools: I ordered the bypass door kits from Home Building Centre, Gravenhurst (contact Bob Collins).

Inspections:  Plumbing and Electrical (arranged by contractors)