THIS WEEK:

-  COMPLETE  2" FOAM BOARD AROUND TOP OF WALL
- DISSASSEMBLE SHELVES IN STORAGE CAN, RETURN TO DAN LACROIX
- EMPTY STORAGE CAN AND CONTACT CRS TO REMOVE
- BUILD INSULATED WALL AROUND PORCH WALL IN BASEMENT
- DRYWALL BASEMENT STAIRS
- DRYWALL AND CORNER BEAD ON WINDOWS IN 1014
- RIP 1X PINE TO BUILD OUT JANBS AT SIDE DOORS

ON THE CRITICAL PATH BY 3RD END OF WEEK IN NOVEMBER:
- PARGING BASEMENT WALL -- HOWARD/CONTRACTOR
- ORDER AND GRADE SOIL FILL AROUND BASEMENT WALLS -- HOWARD BRENTQUARRIES, TED SMITH, JEFF OVERBEEK
- BUILD AND INSTALL RAMP AND STEPS AT SIDE DOOR AND FRONT-- CONTRACTOR/HOWARD
- POUR PORCH SLABS --- SOLID CONCRETE/HOWARD
- INSTALL SIDING -- WESTERBY SIDING/HOWARD/CONTRACTOR
- PAINT PRIMER AND COLORS -- VOLUNTEERS/BRIAN
- HEATING AND HRV INSTALLATION -- MARTINO, HPN/HOWARD 
- COMPLETE PLUMBING