Thursday, October 14, 2010

Climbing the walls

ON SITE SUPERVISOR: HOWARD RUTTAN

VOLUNTEERS: KENT HAMILL, MIKE GUERY, ROB ABBOTT

CONTRACTORS: JEFF VINCENT (VINCENT ROOFING) DISCUSSED PLANNED ROOF INSTALLATION.(ABOUT 2 WEEKS)
                         BOB DUKES (ABC DRYWALL) CAME IN AT 5 PM AND STAYED TILL 8 PM. HE WILL CARRY ON WITH DRYWALLING FOLLOWING THE FESTIVAL WHEN HE FEELS HE WILL HAVE MORE TIME AVAILABLE.
                         CONTACTED HPN AND THEY PLAN TO SEND THEIR GUY OUT TOMORROW FOR PLUMBING

ACTIVITIES: KENT, MIKE AND ROB COMPLETED DRYWALL IN 1014A. MIKE AND KENT MOVED TO 1014 TO CONTINUE DRYWALLING. ROB TOOK ANOTHER LOAD TO THE DUMP.

VOLUNTEER REQUIREMENTS: LOTS NEEDED

NEXT: DRYWALL CEILING IN 1014. THEN CONTINUE WITH WALLS.

~HOWARD RUTTAN 

No comments: