Wednesday, September 15, 2010

Tyvek wraps it up

Patty Parson's Build Daily Log

Date:Sept. 15

On Site:  Frank J. Fraser
             Site Supervisor

Volunteers: It was a light day.  Nan Got us going in the morning. Jim Partridge, Paul Dempsey, Peter Hemming, Brian Juniper, with Tom working the afternoon shift.

Contractors: A.D.A.D. The electricians returned again today to continue wiring 1014

Visitors: None

Daily Log: Weather was clear and sunny today. The day started with the delivery of the dry wall. It was unloaded into each of the units. Received the delivery of the Tyvek from Dupont.  Finished capping the stairs in 1014A. Finished the PT capping Then moved onto installing the concrete board on the outside wall. Finished the West wall and back wall.  Started drilling for the Tap cons to hold the lower part of the concrete board till the Hammer Drill decided it didn't was to work any more.

Action / Follow up Items :
PS. Still no plumber. Spoke to their office hoping to come on 0saturday

Next Day / Week Plan: Build frame for knee wall in basements Tyvek exterior in preparation for windows and doors on Saturday. Then onto insulation and dry wall. Additional framing for the roof that was missed.  Check beam lamination,

Elves in the pm 6-9:30
Volunteer Requirements: lots of projects for Volunteers.

Materials / Tools : need Hammer drill and more drills for installation of framing for knee wall, concrete board, drills for drywall.

Inspections:Soon

Prepared By: Frank J. Fraser

Quote of the week :
Rest if you must but never "Quite"