Thursday, September 2, 2010

Sheathing, bracing and nailing and gabling

Construction Daily Log, Patty Parsons Build

Date: September 1, 2010

On Site: 


Site Supervisor: Frank Fraser

Report prepared by: Rob Abbott

Volunteers


Brians: T and J., Jim P., Mike R., Doug, Rob,  and, as usual, Brian McD. And Nan got us going and checked on us through the day.
Lift that bale...
Contractors


Ron Jackson of HPN Plumbing stopped by to review scope of work.


Daily Log: Jeepers! September 1; where did the summer go? We worked on finishing up the walls and framing on 1014A. I left around noon, so if there was anything noteworthy different, Frank will issue an addendum or I'll add to tomorrow's report.
  • Contact Ports heating re furnace - Rob

Next Days/Week Plan:
Thursday-Saturday Finish framing in 1014A, nail trusses on 1014 to party wall top plate. Nail gable end trusses to top plates. 


Fill in sheathing over soffits and gables, stairs on 1014, interior walls on 1014, truss bracing on 1014......

Volunteer Requirements: For the foreseeable future, we should be able to find work for a large crew. Lots of jobs.

Materials/Tools: Air horn, 2 replacement bulbs for work lights, and 2 rough-service bulbs for trouble light. Still waiting on 6” Tapcon screws. GIK drywall delivery scheduled for September 15. Pocket door frame.

Inspections: Soon