Patty Parson's Build Daily Log

Date: Day of Sept. 9

On Site:  Frank J. Fraser
             Site Supervisor

Volunteers:   Nan & Brian Got us going this morning. Rob Abbott, Brian Ternoway, Deb Tilson, Mick Boese, Jim Partridge, Tom Neville


Contractors:  The 3 Electricians from  A.D.A.M. Electrical.  Were on site again today  finishing the wiring in 1014A. One down. One to go.

Daily Log:  We  worked on stair's  for 1014. As well as the fire blocking, backers in the closets. Spoke to the plumber (ya aaa) hopes to drop by the this Saturday to scope it out. Still unable to do the Ice & water shield as the roof still too wet.

Action / Follow up Items:  John will try to return on Saturday. Stephen is going to bring a few friends by to help with the roof as well.



Next Day / Week Plan: finish rough-in framing for 1041. Check beam lamination, foundation PT edging, stairs to basement in 1014.

Elf Crew Tuesday and Thursday Evening 6 pm - 9:30pm
Thursday: No Elf Crew this evening


Volunteer Requirements: lots of projects for Volunteers.

Inspections:"O" so close

Prepared By: Frank J. Fraser