Saturday, September 25, 2010

Patty Parson's Build Daily Log

Date:Sept. 25

On Site:  Frank J. Fraser
             Site Supervisor

Volunteers:  Nan ( the Bala Timex ) Got us going in the morning. Mike Rollin, Peter Hemming, Mike Bradley

Daily Log: Nan (The Bala Timex) got us started. The day started off a little cool by late afternoon it started to rain.  Peter & Mike finished installing the tub and shower enclosures for unit 1014 they will do the one in unit 1014A on Tuesday. Mike Bradley finished the framing of the knee wall in the basements.    Great job guys .

Action / Follow up Items :  insulate the walls, vapor barrier and prep for drywall on Wednesday or Thursday. Re frame eye brow over unit 1014A ( look for Contractor to do it ) Still
No show with furnace people

Next Day / Week Plan:  Finish tyvek  and foam  on upper part of peek walls . Then onto insulation and dry wall. Additional framing for the roof eye brow (to be done by Contractor)  that was  missed.

Elves in the pm 6-9:30
Tuesday:
Thursday:

Volunteer Requirements: lots of projects for Volunteers inside and out. The more the merrier.

Materials / Tools :  shorted on wall and ceiling insulation need sound insulation for party walls. Could always need more drills (hammer) drywall drills never enough tools.

Inspections: inspected  for the rough carpentry and fire block. "Passed" will call for insulation inspection for Thursday.