Thursday, September 23, 2010

Patty Parson's Build Daily Log

Date: Sept. 23

On Site:  Frank J. Fraser
             Site Supervisor

Volunteers:  Nan ( the Bala Timex ) Got us going in the morning. Mike Rollin, Peter Hemming, Ross LeMonnier( one of My Crew leaders from Mississauga Habitat) , Tom Neville, Jim Partridge, Ozzie Jarick.

Contractors: the plumber show up at 3 today to do a little work.

Daily Log: Nan (The Bala Timex) got us started. The day started off a little cool by late afternoon it started to rain. The inspector came in this morning we passed with just 2 deficiencies. That  means we can start putting in the insulation tomorrow morning.   We had a small  turn out of 7 people. Ross & Ted worked on the backing for the stair railings and bathroom  which are now  finished. I had Peter working on side door header, Jim & Mike worked on the framing for the tub and the shower in 1014. Ozzie helped out were he could. I called for the insulation to be delivered in the morning but it wasn't delivered till after the big guy left figures.     Great job guys .

Action / Follow up Items : finish deficiencies insulate the walls, vapor barrier

Next Day / Week Plan: Build frame for knee wall in basements Finish tyvek  and foam  on upper part of peek walls . 2 pieces of concrete left to do in front of 1014A   Then onto insulation and dry wall. Additional framing for the roof that was missed.

Elves in the pm 6-9:30
Tuesday:
Thursday:

Volunteer Requirements: lots of projects for Volunteers.

Materials / Tools : need Hammer drill and more drills for installation of framing for knee wall, concrete board, drills for drywall.

Inspections: inspected  for the rough carpentry and fire block. "Passed"
P.S., they always find something but not enough to stop us.

Prepared By: Frank J. Fraser

No comments: