Thursday, August 5, 2010

We've been framed!

Volunteers:  Rob, Brian, Willie D, Chris, Taylor, Bill, Jordan


Daily Log: The weather was nice.  We had a fantastic crew and made some real progress.  Under Fast Framer Willie's tutelage, we got all the outside walls framed and up.  Bill started organizing the sea container.


Action/Follow-Up Items:
Order SM board for outside
Schedule truss and roofing framers.
Framer Willie


Next Days/Week Plan
Friday – Party walls, continue organizing sea container, level trailer
Saturday – finish party walls, square/level walls
Monday – Howard's back! - start sheathing, interior walls


Volunteers
For this week we have work for as many as able to come.  Minimum 3.

Materials/Tools: 
drywall nails or screws for party wall
poly to protect party wall drywall