Construction Daily Log,   Patty Parsons Build
Date: August 24, 2010
Prepared by:  Rob Abbott

On Site:    Site Supervisor: Rob Abbott
Volunteers:  Brian J. and Nan.
Contractors: Jim North, Kyle, and later Mike

Daily Log:    
Brian and I cut and handed up sheets to Jim and Kyle as required.  Sheathing completed on 1014A.  Made a notice and emergency contact numbers board.  Moved sign to more prominent location.



Had a visit from HFH-Mississauga Site Supervisor, Frank Fraser, who is taking the summer off and has a cottage in the area.


Action/Follow-Up Items: 
•    Pocket Door frames from Muskoka Window and Door – I still want to hold off ordering the interior doors until we've got all the walls framed.
•    Pick up tubs and showers from EMCO in Gravenhurst - Rob


Next Days/Week Plan:
Wednesday – Contractor working on trusses for 1014.  However, we can safely work on 1014A: move shower units into building, truss blocking, stairs, basement blocking, move cement board, install interior walls, etc.
Thursday – Foundation boards, blocking, stairs for 1014.....

Volunteer Requirements:
Wednesday – 3 – 4.  We could have a large number of heavy sheets to be moved around the site.  Note: I will need someone to pick-up tub and shower units from EMCO in Gravenhurst.  They can use my trailer, but need a hitch with 2” ball.
Thursday – Should be able to find work for a large crew.  Lots of jobs.

Materials/Tools:  Fire extinguishers!