Wednesday, July 28, 2010

Latest update on Bala build


Subject: Log July 27

Volunteers:
Oz, Brian, Bill, Chris, Kathy, Taylor, Rebecca, Marnie, (Rebecca's friend), Howard

CRS delivered "ocean can" about 7:30
Everyone worked on floor plate  beam and Rims during intense heat and UV.
Contacted muskoka Lumber for take-offs and lumber for 2 units. Wood was delivered at end of day but no drywall or 2x4"s. Will buy locally.
ADAM electric scheduled for tomorrow am.
Trailer partly emptied. Remainder still to be worked on.

Next:
Keep working on floor and stairs with as many volunteers as available.(10-12)